Permit Requirements by Job Type

Overview

Quick-reference guide to permit requirements by job type for the Dayton metro area (Montgomery County, Greene County, and surrounding jurisdictions). When in doubt, ask the Production Concierge — he is the designated permit point of contact at Spartan. ## Who This Applies To

All install technicians and service technicians who may encounter permitted-scope work. ## Permit Reference by Job Type

| Job Type | Montgomery Co. | Greene Co. | City of Dayton | Action if Unsure |

|----------|---------------|------------|----------------|-----------------|

| Water heater replacement | Usually required | Confirm | Usually required | Ask the Production Concierge |

| Tankless water heater install | Yes | Yes | Yes | Ask the Production Concierge |

| Sewer line replacement | Yes | Yes | Yes + right-of-way possible | Ask the Production Concierge |

| Repiping (whole house) | Yes | Yes | Yes | Ask the Production Concierge |

| Gas line installation/modification | Yes | Yes | Yes | Ask the Production Concierge |

| Backflow preventer install | Yes | Confirm | Yes | Ask the Production Concierge |

| Drain cleaning/snaking | No | No | No | — |

| Fixture replacement (like-for-like) | No | No | No | — |

| Toilet replacement (no rough-in change) | No | No | No | — |

| Sidewalk or right-of-way excavation | Yes — engineering dept | Yes | Yes | Ask the Production Concierge before any digging |

## Important Field Notes

> the Production Concierge is the point of contact for permit questions. "Before starting a job, the need for permits is confirmed. the Production Concierge is the point of contact for permit questions. This ensures compliance and avoids potential legal issues. " — Slack

- Underground/excavation: Always verify with local jurisdiction before starting. Montgomery County generally requires permit for sewer tap replacement; other excavation may need right-of-way permits. - Subcontractors: When subcontractors are responsible for pulling permits, proactively follow up — do not assume they've done it. "If the subcontractor fails to do so, Spartan may need to pull the permit themselves. "

- Isometric drawings: Some counties require an isometric drawing with the permit application. The service/sales department provides these — plan ahead. - Well work: If homeowner is unaware of well location, contact Miami County to check for permits before locating. ## What to Do When Permit Is Required

1. Stop — do NOT start permitted-scope work without permit in process

2. Notify Production Concierge same day

3. Office Admin initiates permit application

4. NTP (Notice to Proceed) process kicks in — see NTP Process SOP

5. Proceed only after permit is confirmed

## Conflicting Information from Inspectors

Field teams have encountered inspectors giving conflicting permit requirements (Greene County underground repairs example). When this happens: log the conflict in ServiceTitan notes and escalate to Production Concierge for a definitive ruling before proceeding. ## Related SOPs

- Permit Application & Requirements (Phase 2)

- Notice to Proceed (NTP) Process (Phase 2)

- Ohio Plumbing Code Essentials

- Permit & Inspection Certification (Phase 4)

Ohio Plumbing Code EssentialsMaterial Specifications & Stan...